The charging pile controller is the board that decides everything and touches almost nothing. It does not switch the current and it does not measure the energy directly; it reads the sensors, runs the state machine, commands the contactor, talks to the vehicle and to the operator, and records what happened. That makes it the most densely populated and the most firmware-dependent board in the charger, and it is where a build that looks fine at AOI can still fail in the field six months later because a storage device was marginal or a real-time clock drifted. Kilandu assembles charging pile controller boards as part of our EV charger PCBA operation.
What sits on a controller board
| Block | Typical content | Manufacturing sensitivity |
|---|---|---|
| Host processor | MCU or applications processor, DDR memory, boot flash | Fine-pitch BGA, impedance-controlled routing, reflow profile |
| Non-volatile storage | eMMC, NAND, FRAM or EEPROM for logs and configuration | BGA or fine-pitch, humidity sensitivity, programming time |
| Secure element / SAM | Tamper-aware device holding keys and certificates | Placement discipline, key handling process, read-back policy |
| Real-time clock | RTC with backup cell or supercapacitor | Cell orientation, shelf-life handling, first-power date recorded |
| Wired network | Ethernet PHY, magnetics, RJ45 with integrated magnetics | Differential pair routing, connector retention |
| Cellular | 4G or LTE Cat-1 module with SIM or eSIM | Module seating, antenna keep-out, shield can, current burst decoupling |
| Local radio | Wi-Fi, Bluetooth, RFID reader front end | Antenna clearance, ground plane continuity, tuning components |
| Field bus | CAN transceiver, RS-485, isolated variants | Isolation, termination, surge protection, ESD |
| Digital I/O | Opto-isolated inputs, relay and MOSFET outputs | Through-hole optos, inductive load suppression, creepage to the field side |
| Analogue front end | Voltage and current sense inputs, temperature channels, references | Accuracy, filtering, thermal EMF, calibration |
| User interface | Display connector, touch controller, LED, buzzer, keypad | Connector retention, cable-side strain relief |
| Power | Isolated DC-DC from the auxiliary rail, sequencing, supervisor | Isolation, inrush, brown-out behaviour |
A controller board is therefore a mixed-technology assembly in the same sense as the AC power board, but for a different reason: not because of high current, but because a modern processor needs fine-pitch SMT while the field-side interfaces need through-hole opto-isolators and connectors that satisfy creepage and mechanical retention requirements.
The BGA and eMMC questions
Two area-array devices decide most of the reliability on a controller board: the processor and the storage. Both are invisible after assembly, and both fail in ways that only appear over temperature or over time.
What we control:
- Moisture. Plastic area-array packages absorb moisture and can crack or delaminate at reflow. Floor-life and bake rules are applied at incoming, and the bake record is part of the lot record rather than an informal step.
- Paste volume. A BGA needs a controlled paste deposit per pad; too little gives an open at one ball, too much gives bridging under the package where it cannot be seen. SPI before reflow is the control, not AOI after.
- Voiding. Some voiding under a thermal pad is acceptable and some is not, depending on the device and the power it dissipates. The limit is agreed with the customer and checked by X-ray.
- Warpage. Large packages on a thin board warp during reflow. Board thickness and copper balance are reviewed at DFM when the package is large relative to the board.
X-ray inspection of hidden joints is covered on our BGA X-ray inspection page, and the acceptance criteria are stated by IPC-A-610 class rather than as a general claim.
Firmware, keys and what a factory can and cannot do
A controller board is not finished when it is soldered. The processor needs firmware, the storage needs a file system, the secure element needs credentials, and the configuration needs a station identifier and a network profile.
We load firmware and read it back to verify. What we do not do is generate, hold or archive a customer's private keys. Where a secure element or a SAM is fitted, the key material is injected either by the customer's own process or with the customer's equipment and under their control, and the board is then handled as a controlled item. This is a deliberate boundary: a factory that keeps copies of customer keys is a liability, not a service.
Networking interfaces and the antenna problem
The controller board is where the outside world connects, and the outside world is not friendly to electronics. Surge on the Ethernet pair, ESD through the RFID antenna, a cellular module that draws a current burst every few hundred milliseconds.
- Ethernet. The magnetics sit between the connector and the PHY. Where an integrated-magnetics jack is used, the isolation is inside the connector and the board only has to route the pairs correctly; where discrete magnetics are used, their placement relative to the PHY and the connector decides whether the link passes EMC. Both are assembled on the line; the difference is in what has to be verified.
- Cellular. The module is a sub-assembly with its own shielding. The board has to give it a ground reference, a clean supply able to deliver the transmit burst, and an antenna path that does not run under a shield can.
- RFID. The reader front end is analogue and its tuning components are sensitive to the board they sit on. A reader that works on the bench and reads at 30 mm instead of 60 mm in the enclosure is usually a ground plane or a tuning issue, not a firmware issue.
- Field bus. Isolated CAN and RS-485 interfaces put a barrier on the board and a transient suppressor on the connector side. The barrier and the suppressor are not interchangeable, and the order matters: suppressor first, then the barrier.
These are the interfaces where DFM review earns its cost, because antenna keep-out and barrier placement cannot be fixed after the first build without a board revision.
Keep-alive behaviour: the RTC and the backup cell
A charging station that loses its clock loses its session log, and a station that loses its log loses its revenue evidence. The controller board therefore carries a backup source for the real-time clock, and that source has a shelf life and a first-power date.
We record the date the backup source was fitted and the date of first power-up, so the customer can compute the remaining life rather than estimate it. Where the backup is a rechargeable cell, the first charge cycle is part of the test flow, not an afterthought. Where it is a primary cell, the handling rule is different — a cell that is fitted and then stored for a year before installation has already spent a year of its life.
Test plan for a controller board
| Test | What it establishes | Notes |
|---|---|---|
| SPI | Paste volume, especially under area-array devices | Every reflow pass |
| AOI | Placement, polarity, solder joints on visible pins | After placement and after reflow |
| X-ray | BGA, eMMC, QFN thermal pads, voiding | Selected builds or every unit per the agreement |
| ICT | Opens, shorts, values, pull-up and termination networks | Before power is applied |
| Boundary scan | Connections on processors that support JTAG | Where the design provides access |
| Programming and read-back | Firmware written, verified, version recorded | Per unit record |
| Functional test | Boot, peripherals, storage read and write, watchdog, RTC | Against the agreed specification |
| Interface test | Ethernet link, cellular attach, CAN and RS-485 traffic, RFID read | Exercised, not merely populated |
| I/O test | Every isolated input and output in both states | Includes the feedback of each output |
| Analogue accuracy | Sense channels against a reference at two points | Calibration values written and recorded |
| Burn-in | Thermal and voltage margin over an agreed duration | Where the programme specifies it |
The interface test is the one that is most often cut and most often regretted. A populated 4G module with an unexercised link passes every electrical test and fails at the site. Our position is that communication is a function to be verified, not a component to be counted — the same principle applies on the AC charger board and on the portable charger.
Assembly constraints
| Parameter | Capability |
|---|---|
| Layer count | 2 to 24 layers; 6 and 8 layer controllers are the common case |
| Minimum trace and space | 3 mil / 3 mil on ½ oz copper |
| Fine pitch | 0.4 mm QFP, 0.5 mm QFN, BGA to 0.4 mm pitch |
| Impedance control | Single-ended and differential, ±10 % typical |
| Via structure | Through, blind and buried on HDI constructions |
| Surface finish | ENIG for fine pitch and press-fit areas; immersion silver or OSP elsewhere |
| Press-fit | Backplane connectors assembled on the line |
| Coating | Acrylic, polyurethane or silicone, connectors and test points masked |
Boards come from our own PCB fabrication operation, which means an impedance or layer-count change does not have to be negotiated with a third party. Multi-layer control boards follow the rules on the multilayer PCB page, and where the controller sits in a warm enclosure, high-Tg laminate is the usual specification.
Coating and enclosure environment
A controller board usually sits behind the power section, in the same enclosure, so it sees the temperature the power stage creates and the humidity the enclosure admits. Coating protects against the second; the first is a derating question the customer resolves and we build to.
We apply acrylic, polyurethane or silicone coating with masking planned from the assembly drawing — connectors, test points, the SIM or eSIM area, antenna contacts and any pressure or pogo contact stay clear. The conformal coating page lists the masking rules and the coverage inspection criteria. Where a board is delivered as a box build, the coating masking and the harness routing are checked together against the enclosure drawing, because a coated connector that has to accept a harness is a service problem waiting to happen.
Where controller builds fail
- Storage device marginal at temperature. The board boots on the bench and fails in a warm cabinet.
- Backup cell exhausted before installation. The clock resets and the log loses its timestamps.
- Populated communication module, unexercised link. Passes test, fails at commissioning.
- Antenna keep-out violated by a late component. Range drops and the fault is blamed on the module.
- Isolated input without its return path. The input reads correctly on the bench and picks up noise in the cabinet.
- Firmware version not recorded per unit. A field update cannot be targeted at the units that need it.
- Key handling undefined. Boards arrive at the customer's plant and have to be re-handled before they can be shipped to site.
What we need to quote a controller board
Gerbers with stack-up and impedance requirements, the BOM with manufacturer part numbers, the firmware file and the programming method, the interface list with the connector types, the I/O list with the voltage and current of each channel, the mechanical drawing including the antenna keep-out, the expected quantity and the acceptance class. Where a secure element is fitted, the key loading arrangement has to be stated with the quotation request, not after the first build. The quotation file checklist lists the full set.
Prototype builds run in 5 to 8 working days with components in stock, volume production in 2 to 5 weeks, and repeat orders in 2 to 3 weeks. There is no fixed minimum order quantity. Processor and cellular module lead times are the usual constraint, so sourcing is settled at quotation — see component sourcing and the MOQ and lead time page. For an early indication, the assembly cost calculator gives a range and the cost breakdown explains what moves it.
Frequently asked
Do you program the secure element?
Firmware yes, keys no. We load firmware and verify by read-back. Key material for a secure element or SAM is injected by the customer's process or with the customer's equipment, and we handle the board as a controlled item afterwards. This keeps key custody where it belongs.
Can you assemble a controller board with a customer-supplied cellular module?
Yes, and it is common when the module is on allocation or when the customer has a qualified part. We build with customer-consigned components against the approved-vendor list, and the module's seating and antenna path are checked at first article.
How do you handle a board that needs both fine-pitch SMT and through-hole terminals?
As a sequenced mixed-technology build: SMT and reflow first, then through-hole by wave or selective soldering so the fine-pitch side is protected, then the mechanical parts. The route is decided at DFM and held for repeat orders. See through-hole assembly and SMT assembly.
What happens if the firmware changes after the first build?
The change is a controlled revision: the file, the version and the affected units are recorded, and the boards are re-programmed and re-tested rather than re-flashed in the field. Whether that is done here or at your plant depends on where the units are, and it is worth agreeing before the first shipment.
Why Kilandu
Fabrication and assembly under one quality system: IATF 16949:2016 (0596984), ISO 9001:2015 (CN27125Q0392R0S), ISO 13485:2016 (35825MDQMS0021R0S), ISO 14001:2015 (CN27125E0142R0S), UL E352816. Acceptance is stated by IPC-A-610 class, inspection gates are described on the quality assurance page, and capacity is on factory capabilities. Boards can ship as assemblies or as a box build, and a full turnkey scope covers sourcing, fabrication and assembly together.
Send the board with the firmware and the interface list. The interface list matters as much as the BOM — it decides the fixture and therefore the test coverage.
Contact the engineering desk · EV charger PCBA overview · DC fast charger boards · Why Kilandu